Challenge: A financially distressed 2500 TCD plant with outdated infrastructure and high energy costs due to external fuel purchase.
Solution: Comprehensive technical audit and phased modernization plan focusing on energy reduction and process debottlenecking.
Result: Plant revived, stabilized, and became profitable on a sustainable basis.
Phases:
Phase 1: Capacity expanded from 2500 TCD to 3600 TCD.
Phase 2: Capacity further increased from 3600 TCD to 5000 TCD (achieving up to 5500 TCD).
Achievement: Won the prestigious National Efficiency Award.
Key Takeaway: Achieved massive capacity jump without any investment in new steam generation section. Massive reduction in steam demand from 54% to 28% on cane.