SED - Spray Engineering Devices Limited
SED - Spray Engineering Devices Limited
Banner

Pidilite Industries Limited, Gujarat

Project

Successful Commissioning and Operation of a Zero Liquid Discharge (ZLD) Plant

●     Client: Pidilite Industries Limited

●     Location: Paria, Valsad, Gujarat, India

●     Technology Provider: Spray Engineering Devices Limited (SED)

About Client

Pidilite Industries Limited is one of India's leading manufacturers of adhesives, construction chemicals, specialty chemicals, consumer and maintenance products. Its prominent brands include Fevicol, Dr. Fixit, M-Seal, Roff, Fevikwik and Araldite.

With a focus on responsible water management, the company undertook wastewater recycling initiatives to recover process water and reduce freshwater consumption in its manufacturing operations.

Challenge

The manufacturing process generated wastewater with high dissolved salt content, making direct discharge difficult.

Conventional biological and primary treatment systems could not adequately reduce the salt load. Discharge restrictions and regulatory requirements further increased the need for an effective wastewater treatment solution.

The key challenges included:

●     High TDS: Wastewater contained 15,000 ppm of Total Dissolved Solids (TDS).

●     Discharge Restrictions: High salinity limited direct discharge into surface water bodies or sewers.

●     Regulatory Compliance: Stringent pollution control requirements called for a Zero Liquid Discharge solution.

●     Water Recovery: The facility needed to recover treated water for reuse and reduce freshwater consumption.

Solution

SED implemented an MVR-based Low Temperature Evaporator (LTE®) system, an advanced industrial MVR evaporator solution, integrated with a drying stage to achieve Zero Liquid Discharge.

The technology uses Mechanical Vapour Recompression (MVR) to recover and reuse the heat contained in generated vapour, reducing the need for external heating.

The process involves five key stages:

  1. Low-Temperature Evaporation: Wastewater is heated under vacuum at approximately 60°C to initiate evaporation.

  2. Vapour Recompression: Generated water vapour is captured and mechanically compressed using an MVR fan/compressor.

  3. Heat Reuse: The compressed vapour's heat is reused to continue the evaporation process, minimising external energy requirements.

  4. Condensate Recovery: The evaporated water is collected as condensate for reuse within the facility.

  5. Final Drying: The concentrated wastewater from the LTE® is sent to a tray dryer to remove the remaining moisture and achieve complete ZLD.

Key Achievements

The MVR-based LTE® system enabled continuous treatment of high-TDS wastewater with the following reported results:

●     Above 95% condensate recovery for reuse.

●     Below 100 ppm TDS in recovered condensate.

●     Below 100 ppm COD in recovered condensate.

●      Condensate pH of 7–8.

●     35% LTE® reject sent to the tray dryer for further treatment.

●     18 kW/m³ power consumption, as reported in the project data.

●     24-hour operation for continuous wastewater treatment.

The integrated evaporation and drying process achieved complete Zero Liquid Discharge, converting the remaining wastewater concentrate into dry solids for disposal.

Project Parameters

Parameter

Specification

Plant capacity

24 KLD

Plant configuration

5 plants at different locations

Feed flow rate

1 m³/hr

Inlet feed

Process wastewater

Operating hours

24 hours

Feed pH

7.45

Feed TDS

15,000 ppm

Feed COD

250 ppm

Feed BOD

100 ppm

Evaporation temperature

Approximately 60°C

Condensate recovery

Above 95%

Condensate TDS

Below 100 ppm

Condensate COD

Below 100 ppm

Condensate pH

7-8

Power consumption

18 kW/m³

Steam requirement

50 kg/hr for 2-3 hours only